Racking Install at new Automated Warehouse

With our partners Haydn & Rollet, Daifuku and Dexion - we now have the first 15,000 pallet spaces installed (out of a total three stage footprint of 115,000 pallets)

📣 An exciting update on the progress of our new Automated Warehouse build in Drury - NZ's first 3PL automated warehouse.

With our partners Haydn & Rollet, Daifuku and Dexion - we now have the first 15,000 pallet spaces installed (out of a total three stage footprint of 115,000 pallets), the first ASRS units are currently being installed and the shuttle buffer install is also in progress. Have a look at the photos below - up to 10 pallets high, it is quite spectacular!

All is on track for Stage One (18,000 pallets) to be completed in January 2024! We have some Customers signed up for a post-peak period move and look forward to organizing some more site visits in the new year to show you this industry-leading new site.

Stay tuned for some more updates on this extraordinary project.

#theheartofourbusinessisyou #automationrevolution #thefuturestateoflogistics #innovationunleashed #logisticsondemand #cardinaldaifukupartnership